Dragonfruit Team Meeting - January 30th, 2017
Updates
Problems
Goals
Authors
Dragonfruit Team Meeting - January 30th, 2017
Attended: Kevin, Gordon, Tyler
Updates
Transmission Test 1
Board lasted for 17 hours
Transmission Test 2
Board lasted for 56.3 hours
Transmission Test 3
Board lasted for 57 hours
Printed out the bottom cover and mount of the housing
Kevin completed Gantt Chart
Gordon got all necessary and available parts to populate another board (getting familiar with all the parts of DragonFruit)
Current board ready to deploy (projected to be on roof on Monday)
Problems
Need to print parts
Goals
Deploy board before
Program board 4 and 5
Use these boards for testing
Complete redesign of new board
no parallel voltage planes surrounding charging chip if possible
new GPS and RTC components