Dragonfruit Team Meeting - November, 2016
Attended: Keane, Kevin, Tyler
Updates
Soldered more parts onto PCB #5, version 2
Schematic previously followed found to be for version 1
Version 2 schematic and eagle files found, soldering will continue
Parts on each version are relatively the same, therefore no major changes need to be made
Found a fully soldered version 2 Dragon Fruit PCB on solder bench, labeled as #3
Previously, board #4 was being used to program and deploy, but failed proved to be faulty and stopped transmitting after being handled
Board #3 fully programmed without any problems
Board #3 continues to transmit even after being completely disconnected, then reconnected (board #4 would need to be reprogrammed if this was done)
Board #3 deemed as deployable by firmware
XBee, Sensors, and Housing ready for deployment
Waiting for key to get to roof
Problems
Solved many problems this week
Board #4 still buggy and faulty
Resolved problem of having the wrong schematic version for the PCB design
Goals for this week
Deploy board as soon as we have access to roof (before CDR)
Start creating CDR presentation
complete by Wednesday November 9th
Continue soldering on board #5
Draft a new PCB with Real Time Clock and GPS
Look for GPS that can idle
to solve space issue consider another tier of parts
consider creating another tier on sensor board
same connections to MCP through SDA and SCL