Attended: Keane, Kevin, Tyler
Updates
Continued to solder more parts onto PCB #5, version 2
Ghost voltage confirmed to be a non-issue for board #3
Problems
Goals for this week
Deploy board as soon as we have access to roof (before CDR)
Finalize CDR presentation and send to Kaeo to review
Continue soldering on board #5
Draft a new PCB with Real Time Clock and GPS
Look for GPS that can idle
to solve space issue consider another tier of parts
consider creating another tier on sensor board
same connections to MCP through SDA and SCL