Date: 9 April 2018
Date: 11 April 2018
Date: 12 April 2018
Date: 13 April 2018
Authors
Date: 9 April 2018
Attached fan assembly to Wind Tunnel
Tested voltages and speeds
Began sealing outer frame
Date: 11 April 2018
Continued testing of fans installed
Tested existing Teensy and microphone assembly
Wrote test program to confirm functionality
Researching why previous team's programs won't download from Google Drive
Date: 12 April 2018
Testing more of firmware
Will reach out to Scott for additional assistance with program on Google Drive
Began creation of air flow straightener
Date: 13 April 2018
Firmware testing