Date: 12 March 2018
Date: 14 March 2018
Date: 15 March 2018
Date: 16 March 2018
Authors
Date: 12 March 2018
Continued brainstorming constructions aspects of Wind Tunnel
Awaiting additional parts to arrive
Date: 14 March 2018
Received additional parts for Wind Tunnel (including fans, building materials, and additional Teensy devices)
Continued work on Wind Tunnel
Date: 15 March 2018
Tested PC fans for voltage limits (all 4 in parallel)
Constructed second Wind Tunnel shell for testing
Brainstormed how to connect all 4 fans together in a grid
Date: 16 March 2018
Worked on CDR Presentation
Presentation will be next Tuesday due to a member being absent for presentation day
Planned cuts for materials (airflow straightener, plexiglass)