Attended: Brandon, Brian, Kim, Ryan, Christie

  • Students should be following their schedules
  • x96 parts purchase
  • Students should be following their schedules
  • Usual: progress, accomplishments, issues, goals for next week
  • Update progress sheet by Fridays at 11:59 pm
  • Christie will let Kim know what to do for purchases
    • 2 people in 296 team
    • Maybe purchase Sparkfun items
  • Team Rocket still need to purchase parts
  • Zach need to check on access to room for other members as well as training
  • Zach still trying to contact Dr. Garmire for learning to use CNC mill
  • UH Fablab page has tutorials on how to use the mill
  • Charging Circuit
    • Get voltage reading
  • Get teams on track or ahead of time
  • Account for milling time
    • Will take 2-3 hours to mill one PCB
  • XBee
    • Kenny will send out notes on the XBee
    • Check voltage of XBee
      • Could use power supply
  • Bare Arduino with FTDI
    • Christie will post notes on how to do this
  • Eagle Schematic
    • Tryston made 5V switch
    • Teams will need to make humidity switch
  • No Tuesday hours since no AC and power outage
  • Will ask leadership team or mentors to help keep hours open
  • Will send out hours
  • No mentorship meeting
  • Project Badger
  • Team Nova
    • Housing
    • PCB
    • System Integration
    • Need to do bare Arduino with FTDI
    • Need to check sensor code with Ryan
    • Need to verify charging circuit values
    • Need to get XBee working without serial monitor
    • Behind by less than a week
  • Team Black Hole
    • Makamae working on Eagle
    • Humidity sensor working on bare Arduino
      • Works sometimes
    • Did not get temperature sensor working
    • Two weeks behind
  • Team Asteroid
    • Got bare Arduino working with FTDI
    • Starting to make stand alone code
    • Gordon started on housing
    • Still working on XBee
  • Team Rocket
    • Andrew got XBee working with XCTU
    • Emily finished with sensors on Eagle schematic
    • Jennifer working on code for sensors
    • Still need to finish charging circuit
    • Week behind
  • Team Quasar
    • Sensor code done
      • Need to see results for pyranometer
    • Jaimie working on XBee
      • Started integrating XBee code and sensor code
    • Kyaw working on Eagle schematic and getting help from Tryston
    • Need to check values for charging circuit that Kyaw got
    • Week behind
  • Need XBee help
    • Someone should check XBees