Meeting Minutes April 2nd, 2021
Attended: Lauryn, Francis, Brian, Thiri, Yin
Updates
- set up mesh network successfully
- relay was able to work
- tested mesh network with v4.0; successfully worked
- Concluded: if power source fails for relay, message/packet wont receive.
- unable to successfully w/ apple xbee
- cancelled lab on Sunday, April 4th.
- CDR Presentation on Saturday, April 3rd, @ 9am -12pm
To Do
- Finish CDR presentation
- testing many to one; building to building
- testing xbee with other hardware teams (apple and guava)
- Mesh network documentation
Meeting Minutes April 5th, 2021
Attended: Lauryn, Francis, Brian, Yin, Thiri
Updates
- Planned for what to do on next lab meeting
- Thinking about just doing more range testing
- Francis + Lauryn Discussed about 496 presentation Requirements
To Do
- Range testing
Authors
Contributing authors:
Created by lcorpuz on 2021/04/02 22:50.