Date: 9 April 2018

  • Attached fan assembly to Wind Tunnel
  • Tested voltages and speeds
  • Began sealing outer frame

Date: 11 April 2018

  • Continued testing of fans installed
  • Tested existing Teensy and microphone assembly
  • Wrote test program to confirm functionality
  • Researching why previous team's programs won't download from Google Drive

Date: 12 April 2018

  • Testing more of firmware
  • Will reach out to Scott for additional assistance with program on Google Drive
  • Began creation of air flow straightener

Date: 13 April 2018

  • Firmware testing