   * Tim and Allie: Creating a GUI   * Tim and Allie: Creating a GUI
 Project Timeline - 13 weeks Project Timeline - 13 weeks
 +
 ** Hardware ** ** Hardware **
   * Week 1 - Research   * Week 1 - Research
Line 24: Line 25:
   * Weeks 11 - 13 - Debug and test with firmware   * Weeks 11 - 13 - Debug and test with firmware
 ** Software/​Firmware ** ** Software/​Firmware **
-  * Week 1 - Research GUI building tools (Cute/Glade)+  * Week 1 - Research GUI building tools (Qt/Glade)
   * Week 2 - Start work on GUI   * Week 2 - Start work on GUI
   * Week 3 - Work on GUI   * Week 3 - Work on GUI