instrumentation:cvl:meeting_minutes_january_21_2016

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
instrumentation:cvl:meeting_minutes_january_21_2016 [2016/01/21 23:00]
akim
instrumentation:cvl:meeting_minutes_january_21_2016 [2021/09/19 21:59] (current)
Line 25: Line 25:
   * Weeks 11 - 13 - Debug and test with firmware   * Weeks 11 - 13 - Debug and test with firmware
 ** Software/​Firmware ** ** Software/​Firmware **
-  * Week 1 - Research GUI building tools (Cute/Glade)+  * Week 1 - Research GUI building tools (Qt/Glade)
   * Week 2 - Start work on GUI   * Week 2 - Start work on GUI
   * Week 3 - Work on GUI   * Week 3 - Work on GUI
  • instrumentation/cvl/meeting_minutes_january_21_2016.1453417231.txt.gz
  • Last modified: 2021/09/19 21:59
  • (external edit)