weatherbox:team_nova:meeting_minutes_february_29_2016

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
weatherbox:team_nova:meeting_minutes_february_29_2016 [2016/03/04 01:51]
tyamauchi [Reminders]
weatherbox:team_nova:meeting_minutes_february_29_2016 [2021/09/19 21:59] (current)
Line 9: Line 9:
       * On/Off Switch\\       * On/Off Switch\\
   * Finished schematics in Eagle\\   * Finished schematics in Eagle\\
 +  * All sensors now completed\\
 +  * Tested and wrote code for:\\
 +      * Irradiance Sensor\\
 +      * Temperature Sensor\\
   * Xbee: Able to send packet from receiving Xbee to "​weather box" Xbee\\   * Xbee: Able to send packet from receiving Xbee to "​weather box" Xbee\\
       * Unnecessary extra unknown data being read\\       * Unnecessary extra unknown data being read\\
 =====Problems===== =====Problems=====
   * Behind on PCB design but completing parts comes first   * Behind on PCB design but completing parts comes first
 +  * Next week of the 7th, both Tyler and Garret will be off island\\
 =====Reminders===== =====Reminders=====
   * Start PCB design\\   * Start PCB design\\
-  * Finish testing Irradiance Sensor\\ 
   * Complete testing on Xbee\\   * Complete testing on Xbee\\
 +  * Make changes to Preliminary Design Review\\