Dragonfruit Team Meeting - October 30th, 2017
Attended: Kevin, Kyaw, Tyler
Updates 11/6
- Started Critical Design Review presentation
- Spoke to Dr. Garmire about taking down board
- Made edits to housing
- Hole for power cycling
- closing off holes on the top
- Updated SCEL Inventory
Tasks
Contact Dr. Garmire about rooftop access- Review csv file for Weatherbox deployment analysis
Make sure desoldered boost converter acts the way we want it to- Housing for board
- Make Critical Design Review presentation
- Take board down from roof
- Review theories for intermittent transmission
- Final Paper due Friday Dec 15
- Final Presentation Dec 2nd
- Use up Ron Ho Fund