Early March (Pre-Spring Break) - Finish sensor testing
End of March - Finish PCB design
End of April - Finish housing design
Finals Week - Deploy on rooftop
weatherbox:snapdragon:goals
This is an old revision of the document!
Early March (Pre-Spring Break) - Finish sensor testing
End of March - Finish PCB design
End of April - Finish housing design
Finals Week - Deploy on rooftop