weatherbox:cranberry:meeting_minutes_january_24_2018 [2018/01/25 22:52]
ekane
weatherbox:cranberry:meeting_minutes_january_24_2018 [2021/09/19 21:59] (current)
Line 3: Line 3:
   * Started working on Proposal Presentation   * Started working on Proposal Presentation
   * Fixed wiring on the PCB for 4.1 (main and schematic)   * Fixed wiring on the PCB for 4.1 (main and schematic)
-  * Order PCB through Bay Area Circuits ​+  * Ordered 3 Cranberry 4.1 PCB through Bay Area Circuits ​