Members present: Arnold, Raellis, Thomas

  • Completing 3 tasks (Rooftop Sensor Board- REIS 296 Weatherbox Schematic)
  • Hardware, building breadboard: Arnold
  • Coding for Hardware: Thomas
  • EAGLE (rooftop sensor board): Raellis

Members present: Arnold, Raellis, Thomas

  • Continue with the tasks given on Feb. 21