Team Apple Meeting Minutes for Week of October 28, 2019
Updates
- Update Keoni and Noah about Apple v4.1.1 and Apple v4.1.0
- Archiving Wiki Apple Spring 2019
- We were able to send data packets to the firmware database
- Trying to fix voltage problems
- Update Eagle schematic and PCB to have the RX connected to pin 2 and TX connected to pin 9 on the Pro Mini.
- Continue making more PCB boards and taking apart the old ones to reuse their female/male headers
- Update Wiki
Convert Eagle Files to Gerber Files: Make sure to be in “Board Eagle Window”
- change with the dimension readings from “inch” to “mm” since SEEED Studio only takes
- them in “mm”, right click on the dimension arrows where it'll eventually light up and pop-up options
- → Properties → click on “Unit” to change from inch to mm then follow below
- → File → CAM Processor… → CAM Processor window will pop-up takes 3 seconds
- → check box “Export as ZIP”, you may check over the individual layers on the left side under “Gerber”
- → Finally click “Process Job” → save the ZIP file in your desired directory → OK → “Discard”
To save pictures of the Eagle Schematic and Board:
- → File → Export → Image → Browse (for desired directory to be saved in) → OK
SEEED Studio Options
- → Google “seeed studio pcb” → click on “Fusion PCB/PCBA - Seeed Studio” → Add Gerber Files
- → Mostly everything stays the same except the dimensions *Units in mm, desired PCB color,
- and maybe the number of layers if more than the usual 2 layers (or less)
Reminders
- Critical Design Review (CDR) on Saturday, 11/16
- RonHo order (Voltage Regulators) scheduled delivery on the end of October (delayed)
- Mid Semester Progress Report due Thursday, 10/31