Attended: Brian, Garrett

  • Almost done routing board
    • Hopefully will be able to send board out next week
  • Finished power budget and BOM
  • Continue working on CDR
  • Probably will not send out board till other teams verify schematic is correct
  • N/A
  • Finish up the schematic
  • Finish routing board
  • Critical Design Review - November 21, 2015
  • Start poster presentation and paper