October 20 2020
Finished bootloading and programing the 3rd board, attempted to wirelessly communicate XBee to gateway but it didn't work. Blake did not show up into lab due to feeling sick, but worked on bare guava remotely.
Members: Blake, Diwen, Max, Riley Time: 5:00 PM - 8:00 PM
October 8 2020
Worked on Critical Design Review report, and update meeting minutes. Worked with team Firmware on reprogramming board but not sure if it reprogrammed correctly.