Verification Team Meeting - November 06, 2015
Attended: May Chen, Kristie Lee, Dr. Kuh
Progress Check
- Will be using ATmega 328P-PU for Verification Board MCU
- Started documentation for MCU (on Google Drive)
- We want to start getting familiar with this part
- Learning how to set it up, program it, etc.
- Apple documentation
- Updating this document will be an ongoing process
Tasks
- Goals for the next two weeks
- Have a clear-cut idea of what our board will be capable of, etc.
- Have a rough layout for board design
- We will be meeting with Jon about this on Monday
- Goal by the end of the semester
- Have board design ready to be sent out
- Continue to update documentation
Completed
- Met with Apple team and documented changes to Apple design
- Solar irradiance sensor updated to APOGEE-SP215
- Without op-amp
- Updating schematic to reorganize & clean it up
- Working on housing design
- Pressure sensor updated to BMP180
Questions
- May need more assistance with designing verification board down the road. Haven't gotten that far yet.