Members present: Zach, Logan

  • Transferred EAGLE schematic to board layout
  • Learned to place components onto the board
  • Learned how to route connections between the components(using connections in top and bottom layer)
  • Dealt with routing issues(45 degree angles only, clearance errors, overlapping connections)
  • Learned to copper pour
  • Need to figure out most optimal way to place components in order to make routing easier
  • Reached Gerber step of tutorial