 +==== Meeting Minutes January 29, 2018 ====
 +**Attended: Alex(s), Kayla, Becky**
 +
 +=== Updates === 
 +  * Inventory taken
 +        * No parts order needed
 +  * Updated Dr. Kuh on progress/​next steps
 +  * Began working on Proposal Presentation
 +  * Updated Gantt Chart
 +
 +===To Do===
 +  * Get with housing team and discuss plans
 +  * Begin testing
 +  * Proposal Presentation Saturday, February 3rd
 +
 +
 +==== Meeting Minutes February 2, 2018 ====
 +**Attended: Alex(s), Kayla**
 +
 +=== Updates === 
 +  * PCB order was kicked back due to a trace size issue with the voltage regulator
 +        * Issue was addressed, order processed on February 1st
 +  * Learned about range testing
 +  * Filled out EE 496 Poster Session form
 +
 +===To Do===
 +  * Proposal Presentation tomorrow, February 3rd
 +  * Begin firmware modifications
 +
  • weatherbox/bumblebee/week_3_-_january_29_2018.1517253921.txt.gz