+ | ==== Meeting Minutes January 29, 2018 ==== | ||
+ | **Attended: Alex(s), Kayla, Becky** | ||
+ | |||
+ | === Updates === | ||
+ | * Inventory taken | ||
+ | * No parts order needed | ||
+ | * Updated Dr. Kuh on progress/next steps | ||
+ | * Began working on Proposal Presentation | ||
+ | * Updated Gantt Chart | ||
+ | |||
+ | ===To Do=== | ||
+ | * Get with housing team and discuss plans | ||
+ | * Begin testing | ||
+ | * Proposal Presentation Saturday, February 3rd | ||
+ | |||
+ | |||
+ | ==== Meeting Minutes February 2, 2018 ==== | ||
+ | **Attended: Alex(s), Kayla** | ||
+ | |||
+ | === Updates === | ||
+ | * PCB order was kicked back due to a trace size issue with the voltage regulator | ||
+ | * Issue was addressed, order processed on February 1st | ||
+ | * Learned about range testing | ||
+ | * Filled out EE 496 Poster Session form | ||
+ | |||
+ | ===To Do=== | ||
+ | * Proposal Presentation tomorrow, February 3rd | ||
+ | * Begin firmware modifications | ||
+ |