weatherbox:bumblebee:week_3_-_january_29_2018

Attended: Alex(s), Kayla, Becky

Updates

  • Inventory taken
    • No parts order needed
  • Updated Dr. Kuh on progress/next steps
  • Began working on Proposal Presentation
  • Updated Gantt Chart

To Do

  • Get with housing team and discuss plans
  • Begin testing
  • Proposal Presentation Saturday, February 3rd

Attended: Alex(s), Kayla

Updates

  • PCB order was kicked back due to a trace size issue with the voltage regulator
    • Issue was addressed, order processed on February 1st
  • Learned about range testing
  • Filled out EE 496 Poster Session form

To Do

  • Proposal Presentation tomorrow, February 3rd
  • Begin firmware modifications

Authors

Contributing authors:

amoore awong rrupley

Created by awong on 2018/01/29 19:25.

  • weatherbox/bumblebee/week_3_-_january_29_2018.txt
  • Last modified: 2021/09/19 21:59