Week 4
Meeting Minutes September 18, 2018
Attended: Mizpah, Sharmaine, Xiao
Updates
- Referred to previous final reports to fully understand the process they did
- found out new information that may help us
- began Ron ho fund step 1
To Do
- test current bumblebee board
- ask 16MHz vs 8MHz clock.
- finish new PCB layout
Meeting Minutes September 19, 2018
Updates
- Met with Mark to ask questions
- VCC: voltage coming from the solar panel
- 18pF capacitor: might have to order
- Microprocessor: could keep the current microprocessor
- Clock: have to follow the schematic (8MHz)
To Do
- Upload current schematic and PCB layout to google drive
- Range Testing with bare board and another XBee
Meeting Minutes September 21, 2018
Updates
- waiting for the 18pF capacitor
- tried implementing the design based on past bumblebee team's suggestion
To Do
- Powerpoint
Authors
Contributing authors: