weatherbox:bumblebee:week_7_-_february_25_2019

Attended: Mizpah, Sharmaine, Xiao

Updates

* Completed PCB design

  1. Asked Kenneth if all connections are correct
  2. Verified dimensions of breakout board

To Do

  • Order PCB

Attended: Mizpah, Sharmaine, Xiao

Updates

  • Still waiting for Dr. Kuh to send signed ordered forms
  • was going to do range testing using XBee S2C, but bare Bumblebee board was not working
    1. couldn't upload program: not in sync error
    2. solution: changed wires to smaller one (exact size)
      1. reupload blink program –> worked

To Do

  • reupload relay code to bare Bumblebee board
  • Conduct range testing using S2C