People Absent: None

  • Josh continued working on the schematic.
    • Parts order due by this Friday
  • Mark started making Powerpoint presentation.
    • Reusing the same theme as project proposal
    • Josh started gathering part's package description
      • Mark is assigned to complete this
  • Emily started making a block diagram of weather box.
    • Uses pre-existing block diagram as reference

People Absent: None

  • Members updates resumes
  • Josh continues on schematics
  • Mark continues on PDR Presentation
    • updated the gantt charts
  • Emily completed block diagram
    • Assisted with slideshow